The governmentwide goal is 5%
The Small Business Act, at 15 U.S.C. 644(g)(1)(A)(ii), sets the governmentwide goal for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) at “not less than 5 percent of the total value of all prime contract and subcontract awards for each fiscal year.” It was 3% until the National Defense Authorization Act for Fiscal Year 2024 (Pub. L. 118-31, §863), enacted December 22, 2023, changed it to 5%. The SBA puts it plainly: the federal government aims to award at least 5% of all federal contracting dollars to SDVOSBs each year.
That 5% belongs to the government as a whole, counted across prime and subcontract dollars. What binds a prime is the SDVOSB goal in its own approved subcontracting plan.
Where your SDVOSB goal comes from
Under FAR 19.702, a contract expected to exceed $900,000 ($2 million for construction) that has subcontracting possibilities needs a subcontracting plan from the offeror selected for award. The clause at FAR 52.219-9 doesn’t apply to small businesses. For everyone else, it sets what the plan holds and what you report:
- Separate goals for small, veteran-owned, service-disabled veteran-owned, HUBZone, small disadvantaged, and women-owned small businesses, in total dollars and as a percentage of total planned subcontracting dollars. If the contracting officer requires it, an individual plan also states its goals as a percentage of total contract dollars.
- Individual Subcontract Reports (ISRs) for each contract with an individual plan, twice a year, for the periods ending March 31 and September 30, due 30 days after each period closes, plus one within 30 days of contract completion.
- A Summary Subcontract Report (SSR) every year by October 30, covering the 12 months ending September 30.
Check which version of Part 19 your contract or task order carries. The FAR as codified keeps these rules in subpart 19.7. Agencies including DOE and DoD have issued Revolutionary FAR Overhaul (RFO) deviations for Part 19, and the RFO text moves the same requirements to 19.109, 19.206, and 19.302. It keeps the $900,000 threshold ($2 million for construction of a public facility) and has the contracting officer confirm that you file subcontracting reports in SAM.gov’s Subcontracting Plan Reporting (SPR) within 45 days after each reporting period ends.
Which SDVOSB subcontracts count
Three tests decide whether a subcontract counts toward your SDVOSB goal.
- SBA has certified the firm. Section 864 of the FY2024 NDAA requires every subcontract counted toward SDVOSB goals to go to a firm certified by SBA. As SBA’s rule explains, that took effect October 1, 2024, and the certification comes from SBA’s Veteran Small Business Certification program (VetCert). SBA’s clarification confirms that the self-certification grace period ended December 22, 2024. Under 13 CFR 128.200(c)(2), a firm that applied by that date may keep self-certifying until SBA decides its application. A firm that didn’t apply can no longer self-certify for a subcontract that counts. The RFO text agrees: to be eligible under a subcontracting plan, an SDVOSB must be certified by SBA. The codified FAR 19.703 still lets a prime accept a subcontractor’s representation of its status, so don’t stop at a box checked on a quote. Look the firm up: SBA certifications appear in SBA’s Small Business Search (RFO 19.101), and a certified firm’s SAM record shows it as an SDVOSB certified by SBA (FAR 2.101).
- It’s small for the subcontract. For subcontracting, FAR 19.703(a)(1) measures size against the size standard for the NAICS code that you, the prime, determine best describes what the subcontract buys.
- It’s your first tier. 13 CFR 125.3(a)(1)(i) limits reported subcontract awards to your immediate next-tier subcontractors, with narrow exceptions, such as credit designated by an Alaska Native Corporation or Indian tribe. If your first-tier sub hands the work to an SDVOSB below it, that SDVOSB’s dollars don’t count toward your goal.
DOE’s ESPC IDIQ: what we could verify
The Federal Energy Management Program (FEMP) says the current DOE IDIQ ESPCs, known as Generation 4, were awarded on August 4, 2023, to 20 ESCOs. Here’s what DOE has published about their SDVOSB goal:
- The 3% figure. A July 2023 DOE presentation by the DOE ESPC IDIQ contracting officer lists the minimum goals for Generation 4 as “45% overall, 6% for SDB, 5% for WOSB, 3% for HUBZone, VOSB, SDVOSB.” The same deck lists specific ECM installation among the small-business opportunities after award.
- The plan template. The Generation 4 generic contract includes a subcontracting plan template (Attachment J-9). Its example table shows 3.00% for SDVOSBs per project, and it says task-order goals can’t be negotiated lower than the minimum goals DOE requires.
- Task orders. DOE’s Generation 4 ordering guide (Revision 1, August 2024) says every Generation 4 ESCO is a large business with an approved individual subcontracting plan in its IDIQ contract. An ordering agency can set its own goals for a task order, but they must be equal to or greater than the IDIQ minimums. ESCOs must also publicly post every subcontracting opportunity of $250,000 or more on each ESPC project, unless a FAR 5.202 exception applies.
What we couldn’t verify: each ESCO’s approved plan isn’t public, so we can’t confirm any one ESCO’s SDVOSB number. We also found no DOE document that updates the Generation 4 minimum since the governmentwide goal rose to 5%. For your own projects, the numbers that govern are in your IDIQ plan and the task-order RFP.
How the numbers compare
The 5% and the 3% aren’t measured against the same base.
| Goal | Applies to | Measured against | Source |
|---|---|---|---|
| 5% SDVOSB | The federal government as a whole | All prime contract and subcontract awards in a fiscal year | 15 U.S.C. 644(g)(1)(A)(ii) |
| 3% SDVOSB minimum | DOE Generation 4 ESPC IDIQ contracts (2023) | Total planned subcontracting dollars | DOE presentation, July 2023; Attachment J-9 |
| Your plan’s SDVOSB goal | Your contract or task order | Total planned subcontracting dollars, plus total contract dollars if the contracting officer requires it | FAR 52.219-9(d)(1) |
How we work with ESCOs
We’re an SBA-certified SDVOSB. Our President, Bob Melton, is the service-disabled veteran; he served in the Mississippi Army National Guard’s 223rd Combat Engineering Unit. We don’t broker the labor: our own licensed electricians and apprentices in DOL-approved apprenticeship programs install every job. So when we’re your first-tier lighting subcontractor, the work and the dollars sit at the tier your plan counts. Check our certification the same way you’d check anyone’s, in SAM or SBA’s Small Business Search, under our legal name, A Total Solution LLC (Lighting Retrofitters USA is its DBA).
See how we work with ESCOs, or send us a project to price.
Sources
- 15 U.S.C. 644, Awards or contracts (United States Code, 2023 edition)U.S. Government Publishing Office (GovInfo), 2023 edition, including Pub. L. 118-31 (December 22, 2023)
- Veteran contracting assistance programsU.S. Small Business Administration, Accessed November 20, 2026
- Eliminating Self-Certification for Service-Disabled Veteran-Owned Small Businesses (direct final rule, 89 FR 48266)U.S. Small Business Administration, Federal Register, June 6, 2024
- Clarification To Direct Final Rule on Eliminating Self-Certification for Service-Disabled Veteran-Owned Small Businesses (89 FR 62653)U.S. Small Business Administration, Federal Register, August 1, 2024
- 13 CFR 128.200, Requirements to qualify as a VOSB or SDVOSBElectronic Code of Federal Regulations, Current as of November 17, 2026
- 13 CFR 125.3, Types of subcontracting assistance available to small businessesElectronic Code of Federal Regulations, Current as of November 17, 2026
- FAR 19.702, Statutory requirementsAcquisition.gov (FAR Council), FAC 2026-01, effective March 13, 2026
- FAR 19.703, Eligibility requirements for participating in the programAcquisition.gov (FAR Council), FAC 2026-01, effective March 13, 2026
- FAR 52.219-9, Small Business Subcontracting Plan (Jan 2025)Acquisition.gov (FAR Council), FAC 2026-01, effective March 13, 2026
- FAR 2.101, Definitions (service-disabled veteran-owned small business concern)Acquisition.gov (FAR Council), FAC 2026-01, effective March 13, 2026
- FAR Overhaul: Part 19, Small Business (model deviation text)Acquisition.gov (Office of Federal Procurement Policy, FAR Council), Issued September 26, 2025; updated February 20, 2026
- FAR Overhaul part deviation guide (agency deviations by part)Acquisition.gov (Office of Federal Procurement Policy), Accessed November 20, 2026
- Energy Service CompaniesU.S. Department of Energy, Federal Energy Management Program, Accessed November 20, 2026
- Doing Business with DOE’s Office of Energy Efficiency and Renewable Energy / Office of Federal Energy Management Program (Eric Brandenburg, DOE ESPC IDIQ Contracting Officer)U.S. Department of Energy, July 12, 2023
- 2023 DOE IDIQ ESPC, Generation 4 Generic Contract (including Attachment J-9, Small Business Subcontracting Plan Template)U.S. Department of Energy, August 3, 2023
- Ordering Guide for ESPC Task Orders Under DOE’s IDIQ Multiple Award Contracts, Generation 4 (Final Version, Revision 1)U.S. Department of Energy, Federal Energy Management Program, August 29, 2024