U.S. Department of Veterans Affairs · Lexington, KY · 2024–2025
Replace obsolete lighting, Troy Bowling Campus
Campus-wide replacement of obsolete lighting at the Lexington VA’s Troy Bowling Campus, phased around an active hospital. $1.99M base award, about $2.2M at completion.
$2.2M
at completion, up from a $1.99M base award
- 270-day performance period
- Phased with the VA’s COR
- Prime contractor
The job
The VA’s Network Contracting Office 9 awarded us a contract to replace obsolete lighting throughout the Troy Bowling Campus of the Lexington VA Health Care System, to the statement of work, specifications, and drawings. As the prime contractor, we provided all of the labor, materials, equipment, and supervision.
A hospital that never closed
The campus kept running as a hospital the whole time. We phased the work area by area with the VA’s Contracting Officer’s Representative (COR) and Alternate COR, keeping disruption to hospital operations to a minimum.
The results
- Delivered from award through final completion
- Scope grew during performance, taking the contract from a $1.99 million base award to about $2.2 million, and we held schedule and quality throughout
- Minimal disruption to an active VA medical campus
In 2025 we came back to upgrade the campus garage lighting.
Have a building like this one?
ESCOs: send the fixture schedule and we’ll price the labor. Building owners: we’ll start with a free lighting audit.
Buildings over 75,000 sq ft may not qualify for a free audit. A full hospital, for example, can take two weeks to audit.